Painted Prairie
Aurora, CO
Multi-phase development with extensive grading, utilities, stormwater systems, and paving
Located in Aurora, CO, the Painted Prairie project is a multi-phase mixed-use development featuring extensive grading, utility installations, stormwater systems, and paving. With over 1,000,000 CY of earthwork, 130,000+ LF of water and sanitary lines, and 21 miles of sidewalk completed, the project showcases a strong partnership with the Public Improvement Authority and a commitment to quality.
This multi-year, multi-phase infrastructure project in Aurora, CO, delivered integrated wet utilities, stormwater systems, and surface improvements near a major resort and development area. Through expert coordination and consistent quality, the team successfully managed overlapping scopes, maintained the schedule, and earned repeat work with the client.
Installed over 30,000 LF of reinforced concrete pipe and 150+ storm manholes
Completed 130,000+ LF of water and sanitary lines across multiple phases
Delivered over 100,000 SY of asphalt paving and 21 miles of sidewalk
Managed large-scale earthwork exceeding 1,000,000 CY
Built strong long-term relationship with Public Improvement Authority
Awarded multiple follow-on projects due to performance quality